1. Visual Re-inspection: Verify that all fasteners are secure, porcelain components show no new damage, and seals are intact and properly seated; ensure grounding connections for metal fittings are completed according to the design.
2. Insulation Re-test: Re-measure insulation resistance; the test is considered satisfactory if the decrease compared to pre-installation values does not exceed 10%.
3. Power-Frequency Withstand Voltage Test: Conduct a 1-minute power-frequency withstand voltage test in accordance with standards (e.g., the test voltage for a 110kV insulator is 265kV); replace any units that fail the test.
4. Safety Guidelines: Wear safety harnesses for work at heights; strictly prohibit personnel from standing in hoisting zones; ensure live-line installations are performed by certified electricians; and strictly adhere to electrical safety operating procedures.