Blog

Acceptance Requirements for High-Voltage Insulator Installation

Aug 13, 2026 Leave a message

1. Visual Re-inspection: Verify that all fasteners are secure, porcelain components show no new damage, and seals are intact and properly seated; ensure grounding connections for metal fittings are completed according to the design.

 

2. Insulation Re-test: Re-measure insulation resistance; the test is considered satisfactory if the decrease compared to pre-installation values ​​does not exceed 10%.

 

3. Power-Frequency Withstand Voltage Test: Conduct a 1-minute power-frequency withstand voltage test in accordance with standards (e.g., the test voltage for a 110kV insulator is 265kV); replace any units that fail the test.

 

4. Safety Guidelines: Wear safety harnesses for work at heights; strictly prohibit personnel from standing in hoisting zones; ensure live-line installations are performed by certified electricians; and strictly adhere to electrical safety operating procedures.

Send Inquiry